INFRASTRUCTURES EN ... Filtro Progetti

Torino, Italy

Viaducts for the “Caselle Open Mall”

Railway overpass and road overpasses of the shopping mall.

Category: Road bridges
Services: Preliminary and detailed design
Period: September 2017 – October 2019
Customer: R&P Engineering s.r.l.
Amount: Viaduct on “Rotatoria 1” 4.145.582,07 € S04 (IXb) – Viaduct on “Rotatoria 2” 2.210.702,40 € S04 (IXb) – Railway overpass 1.648.114,38 € S04 (IXb)

The Viaduct on “Rotatoria 1” has a deck with a constant width of 19.8 [m], and it is composed by two carriageways of 8.25 [m] realized with 4 composite I-beams (1.6 [m] height) in a composite steel-concrete system with static layout of a continuous beam with 9 spans, span equal to 27.5 [m], for a total length of approximately 247.5 [m].

The Viaduct on “Rotatoria 1” has a deck with a constant width of 19.8 [m], and it is composed by two carriageways of 8.25 [m] realized with 4 composite I-beams (1.6 [m] height) in a composite steel-concrete system with static layout of a continuous beam with 9 spans, span equal to 27.5 [m], for a total length of approximately 247.5 [m].

The Viaduct on “Rotatoria 2” consists of an upper deck with an 11.1 [m] platform and a 9.60 [m] roadway supported by 3 beams of 2 [m] height in composite steel-concrete I-section with a static layout of a continuous beam with 6 spans, spans equal to 28 [m] in the two side spans and 40 [m] in the four central spans, for a total length of approximately 216 [m].

The Viaduct on “Rotatoria 2” consists of an upper deck with an 11.1 [m] platform and a 9.60 [m] roadway supported by 3 beams of 2 [m] height in composite steel-concrete I-section with a static layout of a continuous beam with 6 spans, spans equal to 28 [m] in the two side spans and 40 [m] in the four central spans, for a total length of approximately 216 [m].

The railway overpass has a deck with an 11.5 m roadway made up of 9 juxtaposed beams 1.25 [m] high in a composite steel-concrete section with an isostatic arrangement over a span equal to 43 [m].

The railway overpass has a deck with an 11.5 m roadway made up of 9 juxtaposed beams 1.25 [m] high in a composite steel-concrete section with an isostatic arrangement over a span equal to 43 [m].